Hagastaden has been built since 2010 on the deck over the E4/E20 motorway and the Värtabanan railway: 7,000 homes and 50,000 workplaces when complete, of which 4,000 homes and 14,000 workplaces on the Stockholm side. Here is what is being built now – the metro, the office buildings, the park and the housing blocks – and the city’s three sub-areas together with Solna’s Norra Hagastaden, due at the earliest in 2041. The green line’s opening to Arenastaden is planned for the fourth quarter of 2028, but since Region Stockholm’s review in September 2026 it is expected in the fourth quarter of 2029 – no new timetable has been decided.

The facts are read from the City of Stockholm’s, Solna municipality’s, Region Stockholm’s and the developers’ own pages, and each section shows when they were last checked. Which streets are dug up this particular week is on the city’s page of ongoing works, which we link to rather than copy.

New homes
7,000
New workplaces
50,000

Under way and coming

Individual buildings with a published timetable. The links go to the city's own project pages.

Tunnelbanestation Hagastaden

Infrastructure · Torsplan / Hagaplan
Region Stockholm (the metro extension)

The green line’s extension from Odenplan towards Arenastaden gets its first new station here, 20 metres below ground. Four entrances off two ticket halls: in an existing building at Torsplan, on Hagaplan, inside Karolinska University Hospital, and at Karolinska Institutet where Nobels väg meets Solnavägen. T-Centralen will be seven minutes away without a change. The artist is Åsa Jungnelius, who dresses the platform hall in shades of pink with several hundred discs in the ceiling that together form the inside of a shell. The opening is planned for the fourth quarter of 2028, but since Region Stockholm’s review in September 2026 it is expected in the fourth quarter of 2029 – no new timetable has been decided. The review was published on nyatunnelbanan.se on 25 September 2026; the station page still says 2028.

Opening planned for Q4 2028; now expected in Q4 2029● Under construction

Kontorsbyggnad på Hagaplan, kvarteret Pavia

Offices · Hagaplan
Vectura Fastigheter

A small office building on top of the metro entrance on Hagaplan: two office floors of 600 square metres each and a ground floor with 160 square metres of premises that includes the station entrance. Designed by 3XN, the same practice as Forskaren next door. The plan is in legal force.

Occupancy spring 2027● Under construction

Infinity, kvarteret Sorbonne

Offices · Centrala Hagastaden
Castellum

An office building of about 24,600 square metres gross between Eugeniavägen and Johanna Hedéns gata, built on top of the road and rail tunnels. Two separate volumes joined by a glazed section, with a shared lounge, café and reception. Foundations were laid in 2020–2022; the frame has been rising since 2025.

Occupancy Q4 2027 (preliminary)● Under construction

Haga Heights

Housing · Norra Stationsparken
Besqab

The city’s plan holds 235 condominiums from studios to five rooms between Hagaesplanaden and Eugeniavägen, with public premises at street level; the frame goes up during 2026. Besqab is selling the first part, Haga Heights with 107 apartments, now, and has the neighbouring Haga Vista with about 140 owner-occupied apartments planned for occupancy in 2029.

Occupancy from Q1 2028 (preliminary)● Under construction

Kvarteren Cambridge och Stanford

Housing · Centrala Hagastaden
Atrium Ljungberg

Two blocks in one: Cambridge with 205 apartments, just over 200 of them condominiums, and Stanford with 22,500 square metres of offices, above the Bellman garage with about 300 spaces. Groundworks for the homes start in summer 2026 and for the offices in spring 2027. The plan is in legal force.

Occupancy 2031 (preliminary)● Under construction

Norra Stationsparken

Park · Centrala Hagastaden
City of Stockholm

The district’s park will be 18,000 square metres, shaped like an hourglass with two arms either side of the waist, and is built in stages as the blocks around it finish. Playgrounds, walks and planting chosen for a site on top of the tunnels; large parts are already finished and in use.

Complete 2030● Under construction

Teknikbyggnad vid infarten till Norra länken

Infrastructure · Uppsalavägen
Skanska

A plant building for the tunnel’s installations at the Uppsalavägen entrance to Norra länken, with a planted roof that handles rainwater. Work began in spring 2025. Climate-improved concrete, recycled steel and HVO-fuelled machinery are to save about 250 tonnes of CO₂ during construction.

Complete by the end of 2026● Under construction

Utbyggnad av gator vid Norrtull

Infrastructure · Norrtull
City of Stockholm

The street network at Norrtull, Sveaplan and Uppsalavägen is being extended and partly rerouted, with several traffic diversions until around 2030. First the eastern part of Norra Stationsgatan and southern Uppsalavägen, December 2025 to 2027; then Sveavägen and Sveaplan 2027–2029, Uppsalavägen 2028–2029 and Annerovägen 2029–2030. A pedestrian and cycle bridge across the square is built 2026–2030.

2025–2030, in stages● Under construction

Kontorshus vid Sveaplan

Offices · Sveaplan
Fabege

An office building with public uses at street level beside the Getingen block at Sveaplan. The plan was adopted by the city planning committee in June 2025, appealed, and gained legal force on 29 December 2025.

Start at the earliest 2026, complete 2029○ Planned

Hagastaden P-hus, östra

Infrastructure · Valfrid Palmgrens gata
Stockholm Parkering

The third and last section of Stockholm Parkering’s garage under the district, entered from Valfrid Palmgrens gata. The first two, västra at Ninni Kronbergs gata and mitt at Dalagatan 71, are open and listed on /service.

Opens 2030 (preliminary)○ Planned

Phases

The city’s three sub-areas on the Stockholm side and Solna’s Norra Hagastaden, with home counts and planning status as the municipalities state them.

Centrala Hagastaden

2013–2030

Occupancy continuous 2013–2030; 300,000 square metres of offices and retail. The plan is in force.

3,100 homes● Under construction

Östra Hagastaden (Norrtull)

The plan gained legal force on 28 February 2025; built in stages. The 9,100-square-metre Norrtull square at the old tollhouses, the 12,000-square-metre Bellevue park and a 180-metre pedestrian and cycle bridge to central Hagastaden. The school and preschool are deferred because of falling birth rates.

600 homes, of which 300 student flats and 90 service flats○ Planned

Västra Hagastaden

Review 20 May–22 June 2026, adoption in the first quarter of 2027, construction at the earliest in the fourth quarter of 2028. About 77,500 square metres of offices and retail, 13,000 of sports and culture, and the junction at Karlbergsvägen becomes a green meeting place.

about 185 apartments○ Planned

Norra Hagastaden (Solna)

–2041/2042

The old hospital site becomes city: about 3,000 homes and 150,000 square metres of premises. The first detailed plan, with 1,200 homes, 70,000 square metres of care premises, a preschool and LSS housing, was out for review 22 June–14 August 2026. The whole area complete at the earliest in 2041–2042.

Region Stockholm as landowner, Locum as developer, Solna municipality plans

about 3,000 homes○ Planned

Source: City of Stockholm (vaxer.stockholm) and Solna municipality · the city's page updated 2026-09-10

Already complete

The buildings the district is known by, with architect, developer and the year they were complete. Several of them are in the directory.

Forskaren — A 24,000-square-metre life-science building with offices, a Tekniska museet exhibition and Urban Deli
In the directory:Urban Deli Hagastaden
3XN for Vectura Fastigheter, built 2020–2024 · complete 2024
Life City — 27,700 square metres of offices and services on the Solna–Stockholm border
In the directory:K-märkt Hagastaden · Trainics
Atrium Ljungberg, complete spring 2022 · complete 2022
Norra Tornen, Innovationen och Helix — Housing – the two towers at Torsplan
OMA (Reinier de Graaf) for Oscar Properties; International Highrise Award 2020 · complete 2020

Source: City of Stockholm (Central Hagastaden) and the developers’ own pages

Every fact checked against the city's own pages on 2026-09-12 or later